25 Units of Bio Diesel Plant Tanks are Built in Dumai Industrial Estate
As much as 25 units of bio diesel plant tanks own PT Ciliandra Perkasa are built PT Wijaya Karya (WIKA) since July 2007 and planned to be completed on March 2008 (8 months) in Dumai industrial area, Pelintung, Medang Kampai, Dumai Riau.
The Tangki Bio diesel Plant-Pelintung-Dumai project consists of two types; mild steel storage tank (53.496 liter) and stainless steel storage tank (6.850 liter) with total capacity: 60.346 liter.
As main contractor, WIKA carries out pile work and mechanical & electrical work of Bio Diesel plant Tank project. WIKA has scope of work i.e. shop drawing, preliminaries, material procurement, fabrication, erection, painting, test and tank finishing while PT Mitra Pemuda has Pile Cap & Pondasi work. Until the end of December 2007, project progress has reach 77, 29% of the plan (66,29%).
During the working project process, project team which led by Agus Pramono is really concern on Safety and Health of work (K3). The team helds safety morning talk, morning exercise, safety award, safety induction and tool box meeting. Included K3 announcement installation, K3 & APAR fringe and K3 slogan in order to increase awareness and understanding of K3.