Jakarta, Indonesia – PT Wijaya Karya (Persero) Tbk (WIKA) has successfully completed the rehabilitation of the Jakarta Convention Center (JCC) and handed over the project to the Ministry of Public Works and Housing (PUPR). The handover ceremony was held on August 25, 2023, and marked the completion of the project in just 72 days.
The JCC rehabilitation project was undertaken with a contract value of Rp 115.9 billion and was aimed at transforming the venue into a modern and iconic landmark that reflects Indonesia's rich cultural heritage. The project was completed in time for the ASEAN Plus Summit 2023, which was held in Jakarta in September 2023.
WIKA's Commitment to Quality and Speed
Despite the tight timeline, WIKA maintained its commitment to delivering high-quality construction. The company will continue to focus on the maintenance of the JCC to ensure its long-term durability and safety.
Aek Tano Ponggol Bridge: Boosting Connectivity and Tourism
WIKA's expertise was also showcased in the construction of the Aek Tano Ponggol Bridge in Samosir Island, North Sumatra. The bridge, which was inaugurated by President Joko Widodo on August 25, 2023, plays a crucial role in connecting the island to the mainland and promoting tourism in the Lake Toba area.
The 465-meter-long bridge features a unique design that incorporates traditional Batak cultural elements, reflecting WIKA's commitment to preserving Indonesia's cultural heritage.
WIKA's Contributions to National Development
The successful completion of the JCC rehabilitation and Aek Tano Ponggol Bridge projects highlights WIKA's capabilities in delivering high-quality infrastructure projects that contribute to Indonesia's national development. The company's commitment to quality, speed, and cultural sensitivity has earned it a reputation as a leading construction company in Indonesia.